3. project meeting

3rd project meeting was organized via teleconference on 23rd and 24th of September 2020.

We reviewed the performed work so far. Some tasks are facing a delay due to the crisis of COVID-19 outbreak.

 

Workshop on Digitalization infrastructure

Workshop on MindSphere cloud platform and Edge Streaming Analytics

Ljubljana, 9.-10. September 2020.

 

Siemens organized a two-day workshop for INEVITABLE project partners, where best practices related to the principles of communication and data infrastructure design were presented.

The hands-on workshop was focused on overview, evaluation and testing of MindSphere cloud platform and Edge Streaming Analytics solution, which would be needed to build end-to-end data platform, providing data acquisition, processing, data analysis and visualisation capabilities.

As travelling and grouping is still restricted due to COVID-19, this workshop was organized only for Slovenian partners.

Thank you, Matjaž Demšar and Boštjan Virant from Siemens Slovenia, for organizing an event

 

Kick-off meeting

Kick-off meeting of the INEVITABLE project took place in Ljubljana on 8th and 9th October.

 

2. project meeting

Due to the travel restrictions caused by Covid-19 outbreak, the 2. project meeting was organized via teleconference only on 24th and 25th of March 2020.

We reviewed the performed work so far. All activities are being carried out as planned.

© Copyright 2019 Inevitable

  

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.